Seti Khola Hydropower Project Launches Test Production with Rs 5.5B Investment

Exterior view of the Seti Khola hydropower facility.

The 22 MW Seti Khola hydropower project has begun test production in Musetoda, Kaski. According to myRepublica, commercial operations are expected to commence after a 15-day testing period starting July 5, 2026. Developed by Seti Hydro Power Pvt Ltd, the project represents a significant investment of Rs 5.5 billion. The capital structure is composed of 75% loans and 25% equity, with Dolma Impact Fund-2 holding a major stake. The plant is estimated to generate 133.43 GWh of electricity annually, which will be evacuated to the national grid through the 132 kV Lekhnath-Damauli transmission line.